Welcome to the This Session – Baseline your Project “On becoming Real World Project Management Professional” : Welcome to the This Session – Baseline your Project “On becoming Real World Project Management Professional” Syed Naqvi, PMP
ssanaqvi@gmail.com
Course Objective : Course Objective After going through this course participants will develop :
An Understanding of basic project management concepts, environment and activities
Develop knowledge and Skill set required for project management and and ability to apply them in managing Projects on Time, In Budget with Quality
Necessary knowledge to pass PMP exam for certified PMP credential
Course Coverage : Course Coverage Project Management Framework
Introduction to PMI, USA and PMP Exam
PMI Process Groups
PMI Knowledge Areas
Professional and Social Responsibilities
Session3 - Objective : Session3 - Objective Recap of the Previous Session
Plan Project and baseline
Scope Schedule
Budget
Quality
Definition of Project and Project Management : Definition of Project and Project Management A Project is a
SMART , Collaborative & Cross Functional
Undertaking
Having Temporary
Organization
&
Project Management
is the
art and science
of
Managing Competing Constraints
(Scope, Schedule, Cost, Quality, Resource)
and
Risks
associated with the project with suitable
trade off ,
to ensure that project goals are met
In an environment which is increasingly becoming
Global & Flat
(Multi-time zone, Multi-regulation, Multi-culture and multi-location virtual team) S: Specific – Scope, Time, Cost Resource, Quality)
M: Measureable,
A: Attainable, R: Risk,
T: Time bond In project number of people with cross functional, culture, location back ground work together towards a common goal
Project Triple Constraints Scope, Schedule and Cost and art of Trade off : Project Triple Constraints Scope, Schedule and Cost and art of Trade off Cost Schedule Scope If, Cost is fixed , Schedule is decided, then Scope need to be adjusted
If, Scope is fixed, Schedule is decided, then Cost need to be adjusted Cost Scope Schedule Triple Trade Off Example Quality
Understanding Project Planning : Understanding Project Planning Project
Charter Proj. Quality
Requirement
Base line Project Plan Proj. Quality
Mgt Plan WP Quality
Requirement RAM Proj. Human
resource
Mgt. Plan RACI Chart Proj.
Communication
Mgt. plan Proj.
Communication
Record Proj.
Procurement
Mgt. plan WP
Procurement
Specification Scope Def
Document
WBS
Baseline Proj. Scope
Mgt Plan ,
WP Def.
document Proj. Schedule
Baseline Proj. Time
Mgt Plan WP
Schedule Proj. cost/
Budget
Baseline Proj. Cost
Mgt Plan WP
Budget WP
procurements
Record Project
Feasibility
Analysis SH
analysis Project
Requirements Risk
Register Proj. Risk
Mgt. Plan Proj. Scope
Mgt Plan Proj. Time
Mgt Plan
Plan Project – Define Scope : Plan Project – Define Scope Definition
Specifying Detailed aka Low level requirements
Objective
Specify all high level requirements in sufficient detail so that they become basis for all project work
Inputs
Project Charter, Requirements Documentation, OPA, PEF
Tools, techniques and practices
Expert Judgment, SME, Product Analysis, Alternatives Identification,
Creative technique – Lateral thinking, Parallel thinking , Facilitated Workshop
Continuous review and early feedback from all relevant stakeholders/SME
Project Constraints
Outputs
Project Scope Statement – Project Scope Description
Scope Exclusion
Outcome
Scope document should have following properties
Fitness for Purpose/Use – In sufficient details so that it can be basis for future project work
5C Quality attributes
Best Practices
Project Scope should be developed in iterative mode
Plan Project: Task – Create WBS Deliverable and Work package : Plan Project: Task – Create WBS Deliverable and Work package WBS - Work Break Down Structure
PBS – Product Work Break Down Structure
OBS - Organization Break Down Structure
TBS - Task Break Down Structure
Scope - WBS – PBS – Deliverables - Work package -- OBS – TBS – Activity – Resource
Resource like time, Human resource, Material and equipments can be assigned at any level of WBS
A deliverable is a contractual work package
Deliverable is contractual, discrete items which require one or more work packages
A work package is a logical unit of discrete work which may be independently scheduled, performed, verified and delivered
Project monitoring is done at Work package level
Plan Project - Task – Create WBS : Plan Project - Task – Create WBS Definition
Decompose Project product or systems into number logical, discrete, hierarchical, Delivery oriented Workpackages
Objective
Should define all the Work in the project and only the work in the project
Work package should be of appropriate granularity – Neither very high nor very low
Its should be possible to do Cost estimate, Schedule, Monitor and Assign responsibility of work package to one person or organization unit.
Inputs
Project requirement document
Project scope document
OPA, EEF
Tools, techniques and practices
Decomposition, Partitioning
Functional Decomposition, Work Decomposition
Each Work package must be is assigned to a control account no.
Each Work package is assign to OBS code
Each work package is a part of RAM(Responsibility Assignment Matrix)
Outputs
WBS documents
Outcome
Each Work package should result in verifiable product, service or result
WBS Example : WBS Example 1.0 Project Design, Manufacturing, Testing, Delivery, E & C Electrical System 1.1System
engineering 1.2Transformer 1.3Motors
Control Center 1.4Motors 1.5Project
Management 1.2.1Transformer 1 1.2.1Transformer 2 1.4.1Motor 1 1.4.2Motor 2 Initiate
project Plan Project Execute
Project Plan Control
Project Close
Project 1.4.2.1Write Specification 1.4.2.2Make RFP 1.4.2.3Receive Proposal 1.4.2.4Evaluate Proposal 1.4.2.5Receive drawing 1.4.2.6Approved drawing 1.4.2.7Visit for inspection 1.4.2.8Give Dispatch clearance 1.6Testing 1.7Delivery 1.8E & C
Plan Project: Task – Verify WBS : Plan Project: Task – Verify WBS Definition
to formally state that deliverable is meets the acceptance criteria for deliverables
Scope, Cost, schedule and quality requirements
Objective
A formal verification that deliverable meets the criteria for fitness for purpose and other quality attributes
Inputs
Project Scope statement, WBS, WBS dictionary,
Requirement document, Requirement Traceability Matrix,
Tools, techniques and practices
Inspection, Testing and measurement
Outputs
Accepted deliverable, Change request
Outcome
All verified deliverables should meet the criteria of fitness for purpose and other quality attributes
Execute project: Task – Control Scope : Execute project: Task – Control Scope Definition
Managing change in Scope
Objective
All Scope change request should go through scope change control process which should decide whether request should be accepted or rejected
All accepted scope change request should be implemented
Relevant stakeholders should be intimated regarding acceptance or rejection of scope
Inputs
Scope Change Request
Tools, techniques and practices
Scope change impact analysis Cost,Schedule and quality
Variance analysis
Outputs
Approve and disapprove Change request
Update in following documents
Project Plan
Project Scope statement, WBS, WBS dictionary,
Requirement document, Requirement Traceability Matrix
Outcome
Scope change should be managed in controlled manner and scope creep in should be avoided .
Project Time Management : Project Time Management Completing Project on time is one of the biggest challenge in Project Management
Project Work should be done not only on time but JIT or Just on Time
Neither early nor late
Project Schedule is prepared in following steps:
Identify Project activities
Identify Activity duration
Identify Activity sequencing
Identify Activity Resource
Identify Project Calendar
Identify Resource Calendar
Identify Project Milestone
Enter Activity start and end date
Identify Project critical path
Plan Project – Define Activities : Plan Project – Define Activities
Plan Project – Define Activity Duration : Plan Project – Define Activity Duration
Plan – Sequence Activities : Plan – Sequence Activities
Plan Project – Sequence activity : Plan Project – Sequence activity A1 A2 SS A1 A2 FF A1 A2 SF A1 A2 FS Begin A1 A3 A2 A4 FS+5 A5 FS - 2 Dummy activities ?
Float and slack ?
Plan Projects – Estimate Activity Duration : Plan Projects – Estimate Activity Duration
Three Point Estimate : Three Point Estimate PE or Pessimistic estimate
OE or optimistic estimate
LE or most likely estimate
RE or realistic estimate RE = (W1*PE+W2*OE+W3*RE)/6
W1, W2, W3 – Weightage
W1+W2+W3 = 6
Plan Project – Estimate activity Resource : Plan Project – Estimate activity Resource
Plan Projects – Schedule Project and Activities : Plan Projects – Schedule Project and Activities
Project schedule monitoring and control : Project schedule monitoring and control Publish a schedule so that each stakeholder should have access to his portion of the schedule
Each person responsible for schedule, should update the schedule at regular interval
There should be a single point of entry for activity status update
Schedule status information should come to the project Manager
Project Manager should take immediate action if there is a schedule variance
Project Costing : Project Costing Costing is done at different time for different purpose
Ball park figure
For Budget
During marketing stage
During project initiation
Accuracy level varies at depending upon timing of the costing
The real challenge in Costing is to avoid under costing or over costing
Cost estimate can be improved with progressive refinement and costing should be periodically reviewed and updated
Project Costing : Project Costing Basic Cost Behavior
Fixed Cost
Variable Cost
Direct and Indirect Cost
Activity based costing or Lifecycle cost
Project Costing : Project Costing Categories of Cost
At project level
Cost of capital, Resource cost, Travel cost
Transportation cost(F&I), Hedging cost
Site infrastructure cost, Project management cost
Spares and warranty cost, Taxes and duties
Cost at work package level
Cost of the work package depends
Specification – what you want
Avoid over or under specification
Quantity -
Work package cost
Every Work package has one main cost and more than one additional cost
It is important to consider main cost as well as all other possible additional costs
Work package life cycle cost
Design, Bought out cost, Manufacturing and assembly cost
Testing cost, Taxes and duties, Transportation cost,
Storage cost, Erection, Commissioning and handing over cost
Project Costing and budgeting : Project Costing and budgeting Cost and Price
The actual money required to deliver a work package /complete the project work
Pricing is the values at which project/work packages are billed to the customers
Costing and budgeting
Costing is the actual monies required to complete the project work
Budget is an expenditure plan to ensure that monies are available to
To meet the work expense requirement over time throughout project lifecycle
Project CAPEX and OPREX budget
Project Inventories, Receivables and Payables
Working Capital Cashflow management
Costing Technique : Costing Technique Analogous Estimate
Parametric Estimate
Three Point Estimate
PE or Pessimistic estimate
OE or optimistic estimate
LE or most likely estimate
RE or realistic estimate RE = (W1*PE+W2*OE+W3*RE)/6
W1, W2, W3 – Weightage
W1+W2+W3 = 6
Thank You : Thank You Syed Naqvi, PMP