Introduction to PM

Add to Favourites
Post to:
Join the Project Management Community

Description
roject management is the discipline of planning, organizing, securing and managing resources to bring about the successful completion of specific project goals and objectives. It is sometimes conflated with program management, however technically that is actually a higher level construction: a group of related and somehow interdependent projects.
A project is a temporary endeavor, having a defined beginning and end (usually constrained by date, but can be by funding or deliverables), undertaken to meet unique goals and objectives,usually to bring about beneficial change or added value. The temporary nature of projects stands in contrast to business as usual (or operations),which are repetitive, permanent or semi-permanent functional work to produce products or services. In practice, the management of these two systems is often found to be quite different, and as such requires the development of distinct technical skills and the adoption of separate management.
The primary challenge of project management is to achieve all of the project goals and objectives while honoring the preconceived project constraints.Typical constraints are scope, time, and budget. The secondary—and more ambitious—challenge is to optimize the allocation and integration of inputs necessary to meet pre-defined objectives.

Comments
Presentation Transcript Presentation Transcript

Slide 1 : REVIEW OF PLANNING AND SCHEDULING ENGR 281

Slide 2 : OUTLINE BASIS FOR PLANNING & SCHEDULING PROCEDURE METHODS GANNT CHART CRITICAL PATH USES FOR SCHEDULE

Slide 3 : PLANNING & SCHEDULING FUNDAMENTAL ENGINEERING FIRST DO THE PROBLEM ANALYSIS THEN DEVELOP A SOLUTION TO THE DEFINED NEEDS SPECIFY OBJECTIVES DETERMINE ACTIVITIES & RESOURCES PRESENT RESULTS IN A SCHEMATIC THAT CAN BE USED BY THE TEAM

Slide 4 : OBJECTIVES FOR PLANNING AND SCHEDULING EFFECTIVE TIME MANAGEMENT OPTIMZE SEQUENCE OF EVENTS DEFINE NECESSARY RESOURCES MONITOR PROJECT PROGRESS

Slide 5 : PROJECT/THESIS PLANNING PROBLEM DEFINITION - SPECIFY HYPOTHESIS AND OVERALL OBJECTIVES DEVELOP SOLUTIONS - DETERMINE METHODS TO TEST HYPOTHESIS TRANSFER INFORMATION TO A SCHEDULE DETERMINE HIERARCHY DEFINE RESOURCE REQUIREMENTS MONITOR PROGRESS OF PROJECT/THESIS

Slide 6 : PRIMARY COMPONENTS IN A PROJECT/THESIS SCHEDULE ACTIVITIES SPECIFIC FUNCTION FINITE DURATION DETERMINE LINKAGE SPECIFY RESOURCE REQUIREMENTS MILESTONES TARGET DELIVERABLES 0 DURATION

Slide 7 : EXAMPLE FOR CLASS ACTIVITY DEVELOP A PLAN TO GET A NEW PRODUCT TO MARKET USE THE DATA PROVIDED IN THIS CHART TO CREAT A GANNT CHART

Slide 8 : TYPICAL GANNT CHART

Slide 9 : CPM (CRITICAL PATH METHOD) USES NODES FOR EVENTS (ACTIVITIES AND MILESTONES) ACTIVITIES ARE CONNECTED WITH ARROWS CRITICAL PATH IS DEFINED TO DETERMINE MINIMUM TIME TO COMPLETE PROJECT

Slide 10 : CRITICAL PATH SEQUENCE OF EVENTS WITH ZERO FLOAT CONTROLS MINIMUM TIME TO COMPLETION NON-CPM ACTIVITIES HAVE FLOAT AND CAN PARALLEL CPM ACTIVITIES CAN BE USED TO OPTIMIZE USE OF RESOURCES AND TIME FOR THE PROJECT

Slide 11 : TRANSFER THE DATA TO A NETWORK DIAGRAM NOTE EACH ACTIVITY AND MILESTONE ARE NODES START/FINISH AND DURATION ARE LISTED ON EACH NODE SYMBOL

Slide 12 : TYPICAL NETWORK DIAGRAM

Slide 13 : PERT DIAGRAMS (PROJECT EVALUATION AND REVIEW TECHNIQUE) PERT IS A CPM THAT SHOWS EARLIEST AND LATEST START TIMES FOR ACTIVITIES USES ARROW PRECENDENCE TO SHOW HIERARCHY INCLUDES FLOAT FOR ACTIVITIES CRITICAL ACTIVITIES ZERO FLOAT EARLIEST AND LATEST START TIMES ARE THE SAME NON-CRITICAL ACTIVITIES HAVE DIFFERENT EARLIEST AND LATEST START TIMES

Slide 14 : FOR EXAMPLE CPM ACTIVITY NON-CPM ACTIVITY LATE START ASSUMES ALL SUBSEQUENT ACTIVITIES USE ZERO FLOAT

Slide 15 : RESOURCE ALLOCATION ANALYSIS OF A SCHEDULE ALLOWS COORDINATION TO ASSURE EFFECTIVE USE OF RESOURCES ELIMINATE PEAKS, VALLEYS DUE TO MOBILIZATION AND DEMOBILIZATION OF RESOURCES

Slide 16 : RESOURCE ALLOCATION Example HIGH ALLOCATION AT START REDUCTION/INCREASE SEQUENCE DAYS 3,4, AND 5

Slide 17 : RESOURCE ALLOCATION Example BY REARRANGING JOB SEQUENCE THE FOLLOWING IS POSSIBLE 1. NOTE THE MAXIMUM REQUIREMENT IS REDUCED 2. THERE IS A SINGLE INCREASE/REDUCTION SEQUENCE

Slide 18 : EXAMPLE OPTIONS ASSUMING THAT ADDITONAL FUNDS WERE AVAILABLE AND THEY COULD REDUCE THE DURATION OF EACH ACTIVITY AS NOTED, DETERMINE HOW THEY SHOULD BE ALLOCATED AND THE IMPACT

Slide 19 : CHECK OPTIONS INITIALLY IGNORE NON-CPM ACTIVITIES CHECK IMPACT BY USING FUNDS ON CRITICAL PATH ITEMS ONE AT A TIME ORIGINAL END DATE IS 01JUL11 THE ANALYSIS INDICATES THE MONEY SHOULD GO IN ACTIVITY 2

Slide 20 : SCHEDULE USE DURING COMPLETION OF PROJECTS AGENDA FOR MEETINGS WITH TEAM & COMMITTEE FREQUENT TRACKING OF PROGRESS SO EFFORT CAN BE OPTIMIZED TYPICAL CONTROL GANNT FOLLOWS

Slide 21 : CONTROL OF PROJECTS

Slide 22 : PRIMARY SOFTWARE PACKAGES MICROSOFT PROJECT (http://www.microsoft.com/project/en/us/default.aspx) PRIMAVERA PROJECT PLANNER (http://www.oracle.com/us/corporate/acquisitions/primavera/index.html ) http://www.umsl.edu/~rbanis/252/ovrheads/pptshows/project.ppt

Slide 23 : SUMMARY PLANNING & SCHEDULING ARE VALUABLE COMMUNICATION AND MANAGEMENT TOOLS FOR PROJECTS PROVIDE AN AGENDA FOR THE PROJECT PROVIDE MEASURE OF PROGRESS PROVIDE BASES FOR OPTIMIZATION

Want to learn?

Sign up and browse through relevant courses.

Name:
Your Email:
Password:
Country:
Contact no:


Area code Number
Subjects you are interested in:
Word verification: (Enter the text as in image)


Sign Up Already a member? Sign In
I agree to WizIQ's User Agreement & Privacy Policy
Taran Bhagat
Primavera, MSPRoject,MATLAB, Project Management
User
1 Member Recommends
26 Followers

Your Facebook Friends on WizIQ

Explore Similar Courses

Online Project Management Professional Certification Prep

Price:$1500
$875

Special Offer: SAVE 40%

Give live classes, create & sell online courses

Try it free Plans & Pricing

Connect